洪益清, 张瑞玺, 霍忠锋, 马亚杰. 东欢坨矿透冲积层黄泥救灾和治理技术[J]. 煤田地质与勘探, 2008, 36(6): 35-37,41.
引用本文: 洪益清, 张瑞玺, 霍忠锋, 马亚杰. 东欢坨矿透冲积层黄泥救灾和治理技术[J]. 煤田地质与勘探, 2008, 36(6): 35-37,41.
HONG Yi-qing, ZHANG Rui-xi, HUO Zhong-feng, MA Ya-jie. Technology and practices in alluvial mud burst disaster relief and control in Donghuantuo coal mine[J]. COAL GEOLOGY & EXPLORATION, 2008, 36(6): 35-37,41.
Citation: HONG Yi-qing, ZHANG Rui-xi, HUO Zhong-feng, MA Ya-jie. Technology and practices in alluvial mud burst disaster relief and control in Donghuantuo coal mine[J]. COAL GEOLOGY & EXPLORATION, 2008, 36(6): 35-37,41.

东欢坨矿透冲积层黄泥救灾和治理技术

Technology and practices in alluvial mud burst disaster relief and control in Donghuantuo coal mine

  • 摘要: 以东欢坨矿-230水平回风巷透冲积层黄泥事故为例,阐述了煤矿沿断层带透冲积层黄泥后采取的排水、控水措施,以及断层突(泥)水通道治理的“注浆封盖、充填灌注、注浆加固”治理方案及效果。

     

    Abstract: Taking the disaster happening in-230 level wind tunnel in Donghuantuo coal mine as example,disaster relief and control are discussed on the fault inducing alluvial mud burst disaster.The following measurements are included:water drainage;water control;three subsection treatment of the mud burst passage,fault,including upper section grouting capping,mid section filling and lower section grouting strengthening;and the control effects.

     

/